The seismic upgrade carried out for the Assisi (PG) headquarters of Sir Safety System Spa, a long-standing client and innovative company from Assisi (PG), present in markets of 30 countries worldwide and a leader in the production of safety products and clothing, was a unique seismic upgrade.
Performed following the demolition of a portion of the building, functional for a subsequent expansion, the intervention was characterized by the use of patented consolidation systems.
In addition to completing the operation in just 45 days, a full week ahead of schedule, the Manini Service designers managed to avoid the use of structures external to the prefabricated building, thus not compromising its logistical functionality or reducing the available space.